What is the difference between duration and work in MS Project?

What is the difference between duration and work in MS Project?

Effort (also referred to as Work) is the actual time required to complete the task. Duration is the total amount of time in which the user has to complete the task. For example, you might have a task that only takes 2 hours to physically complete, but that task can be completed anytime over the next week.

What is a fixed units task?

A task in which the assigned units (or resources) are a fixed value and any changes to the amount of work or the task’s duration does not affect the task’s units. On Fixed Units task, units will be fixed. If you change the work, duration will be changed.

How do I change all tasks to fixed duration?

Select the tasks, click the Tasks tab, select the Information button in the Properties group, click the advanced tab and make the change. I hope this helps.

How does duration work in Microsoft Project?

Duration equals Work divided by Units. Let’s say that Work is 40 hours. The resource is going to work on the task full-time, that is, 100%. Doing the math gives you a Duration of 40 hours, which is the same as five work days.

Why can activity duration be different than the estimated work effort?

The duration depends on the availability and capacity of resources. For example, if you dedicate 3 hours a day to work on the fence, then the duration would be 10 days (30 hours total effort divided by 3 hours/day).

How many categories of work duration are there?

There are actually four calculation types that a task may have in project.net: fixed-work. fixed-duration. fixed-units.

What is a fixed duration?

Fixed Duration is the duration of a task that’s deemed to be constant (fixed). Any changes to the assigned units or work does not affect the duration of the task. Fixed Work is the amount of work of a task that’s deemed to be constant (fixed).

Where can you set fixed duration effort driven and manually schedule?

Change the effort driven setting for task types

  • Double-click the task.
  • In the Task Information box, click the Advanced tab.
  • Uncheck the Effort driven check box. You can add the Effort Driven column to a sheet view. Right-click a column heading and then click Insert Column.

What is fixed duration?

What is difference between effort cost and duration?

The effort is the total estimated time for the realization of a task, of an activity. The duration is instead the time interval required for the realization of the task / activity based on the availability of resources and the project calendar.

How long is the project duration?

Duration is the total time that it takes to complete a project measured in work days, hours or weeks. The duration depends on the availability and capacity of resources. Effort is the number of people hours needed to complete a task, i.e. it’s the actual time that is spent on working on the project.

What does work duration mean?

Duration of the Work means the number of Days from a Job Order Notice to Proceed to Substantial Completion. Duration of the Work means the number of Days from a Job Order Notice To Proceed to Substantial Completion.

What is the difference between fixed work and fixed duration?

Fixed work and fixed duration are common measurements used in assessing the time budgeted in project management. The primary difference between these terms is that work is normally measured in hours, while duration is measured in days. If you plan a whole day to work a task, for instance, the duration is one day and the work is eight hours.

What is the difference between fixed units and fixed duration?

Fixed Duration: The task calendar ‘Duration’ will not change when you change the ‘Work’ or add resources. Fixed Units: The resource percentage of work will not change when you change the task ‘Duration’ or ‘Work’ hours. Fixed Work: The ‘Work’ hours will not change when you change the ‘Duration’ or percentage of resource work.

What does fixed duration mean in Microsoft Project?

Using a fixed duration task type in Microsoft Project. The project manager doesn’t care when the work gets done, as long as it’s in the three day estimate. By setting the task to use a fixed duration task type, the number of hours and resources can fluctuate, and the three day duration will remain constant.

What is difference between working capital and fixed capital?

The key difference between fixed capital and working capital is that fixed capital refers to long-term investments that are not consumed during the production process whereas working capital deals with short-term liquidity (how conveniently an asset can be converted into cash) position in a company.

author

Back to Top